Mining Client - PFAS

Mining

Mining Client, PFAS Water Treatment Plant

SciDev designed, constructed, and operated a water treatment plant (WTP) capable of treating 260ML of PFAS contaminated water for re-use at a confidential site in Western Australia.

The mine site produced low level detections of Per- and Poly-fluoroalkyl Substances (PFAS). A permanent treatment, disposal and discharge solution was required to ensure any PFAS affected operational water is not released to the environment and will provide the most practical and economical use of the water to operate at site.

This PFAS water treatment plant is the only plant in Australia that can treat to the 99th percentile level of protection under the Australian and New Zealand Environment and Conservation Council ANZECC guidelines for discharge to the environment. The strict guidelines were in place due to the site being close to Perth’s Drinking Water Catchment.

Commissioned in November 2020, the PFAS water treatment plant has treated a cumulative total of over 1 billion ML to date, with all water treated down to the lowest level of reporting, without a single detection above 0.0002ug/L sum of total PFAS.

Summary

  • Treated 260ML of PFAS contaminated water in six months.
  • Only PFAS water treatment plant of this scale in Australia treating to beneath the 99th percentile level of ecological protection under the Australian and New Zealand Environment and Conservation Guidelines (ANZECC) for discharge to the environment.
  • The plant’s construction and commissioning were completed in less than 40-days from the contract award to meet operational requirements on site.
  • The water treatment plant is required to operate 24/7 and process 2.5ML/day.

Outcomes

Results

  • 260ML

    Of PFAS-contaminated water treated in six months

  • <40 days

    Construction and commissioning completed in under 40 days from contract award

  • 24/7

    Operations to process 2.5ML/day

Related solutions

Solutions used on this project

More projects

  • Hydra-IQ Case Study

    Mining

    Hydra-IQ™

    Reducing operating costs with Hydra-IQ™

    The deployment of HydraIQ™ revolutionised a mining company’s water monitoring approach, switching from manual sampling to automated, real-time monitoring.

  • Rum Jungle Construction

    Mining

    Reuse & Treatment

    Rum Jungle Mine Remediation

    $19.5 million contract to design and construct a 30 litre pre second multi-stage water treatment plant to remediate contaminated groundwater from legacy uranium mining at the former Rum Jungle Mine.

Talk to our team

Tell us about your site and we'll route your enquiry to the right engineer.

Contact us

Download this resource

Enter your details below and we'll take you straight to the download.

Fields marked with an asterisk (*) are required.