Erskineville Water Treatment Plant
Ward Civil and Environmental Engineering engaged SciDev to design and construct a water treatment plant (WTP) and dewatering system to support civil works at Erskineville, NSW. Groundwater dewatering was required to support open trenching works and trunk main works required below the water table.
Due to the proximity to Sydney Park’s old legacy landfills, groundwater extracted was impacted with an array of contaminants including heavy metals, ammonia, nitrate, nitrite, phosphorus, and hydrocarbons. Water is treated and discharged to the environment under ANZECC 95th percentile level of ecological protection.
Summary
- Designed, constructed, commissioned and operated a water treatment plant capable of treating up to 530m³ of groundwater per day.
- Erskineville required the use of a reactor to perform coagulation, flocculation, and oxidation. The reactor provided a rapid mix/homogenisation capability and efficient chemical use.
- Treated water was buffered to the correct pH and discharged to the environment as required.
- Initially engaged to treat 0.9ML, the WTP processed over 23 megaliters of contaminated water. The only waste generated at the WTP is sludge, pre-classified as General Solid Waste under the NSW EPA Waste Classification Guidelines and was able to be sent to landfill.
Related solutions
Solutions used on this project
More projects
Related projects

Infrastructure
PFAS & Remediation, Dewatering +2 more
Camellia Remediation
Temporary water treatment plant to remove hexavalent chromium and other metals from surface water at Camellia, NSW.

Infrastructure
PFAS & Remediation
Fiskville PFAS Water Treatment Plant
FluorofIX™ implemented for continuous discharge, removing PFAS and oxidisable precursors from contaminated ground and surface water at former CFA training site.

Infrastructure
PFAS & Remediation
Londonderry PFAS Treatment & Capping Works
Temporary water treatment plant that treated 6.9 megalitres of PFAS-impacted water without a single media replacement, alongside capping works remediating two of the site's three retention dams.